Security Update The main passenger security checkpoint construction is progressing. Four passenger screening checkpoint lanes are operational in this location. During high volume travel periods, a secondary passenger security checkpoint - “Checkpoint A” is operational with two checkpoint lanes near the American Airlines Ticketing counter. As a reminder, passengers need to arrive at the Airport 90 minutes prior to their scheduled departure time.

Traffic & Pedestrian Pattern Updates The Upper Level Departures roadway remains open at all times for dropping off departing or picking up arriving passengers. There are partial curb impacts as the old canopy over the existing sidewalk continues to be removed for installation of the new canopy. Pile driving is complete; next steps include forming and pouring concrete footers for the new canopy.

The Arrivals Level remains impacted with detours for various entrances and exits to the terminal and related crosswalks. Shuttle and RTS Bus Pick Up has moved to the west end of the arrivals roadway. All Valet operations (pick up and drop off) are taking place on the lower level arrivals roadway. Rideshare pick up is also taking place on the lower level arrivals roadway. 

Terminal Update The new relocated Hudson News store going in center food court has started installing display cases with plans to have the new store open soon. Temporary construction walls are being installed on the exterior walls of the rotunda’s to prepare for expansion of the terminal building in the coming months.

Ticketing/Gate Update All Airline ticketing counters remain in their current locations from East to West: United Airlines, Air Canada, Southwest, Delta Air Lines, JetBlue, Allegiant & American Airlines.

Parking Update All parking lots remain open. The ROC Airport Smart Phone Lot is open and operating. This lot is located on Airport Way - the first right hand turn as you approach the terminal from Brooks Avenue and is complete with a large flight information display screen. To reduce roadway congestion family and friends picking up passengers are encouraged to use this lot.

 

Bid opportunities currently available for the project can be reviewed at the Monroe County Purchasing website.

Be sure to follow the progress at RocRenovation.com and on social media! We’re on Facebook (facebook.com/ROCAirport) and Twitter (@ROCAirport).

 

Photo:

Old Canopy at West End of the Terminal Fully Removed

 

 

 

 

For General Airport News Visit rocairport.com