Terminal Update All major work on the caissons is complete detailing being addressed next week. Pre-Construction meeting on the entrance canopy was held, preliminary site preparation will begin next week between the parking garage and the terminal. The Hudson News Store (lower level) is near completion and will open early next week. Restroom renovations post-security are nearing completion. Electrical connectivity for the air conditioning control system is progressing.

Terminal/Security/Gate Update Allegiant Airlines ticketing counter has moved to the west between JetBlue Airways and American Airlines. Air Canada will be moving to the east side of passenger lobby next week.

Security Update Passenger Security Checkpoint construction project has commenced.

Parking Update All parking lots remain open. The new ROC Airport Smart Phone Lot is open and operating. 

Traffic Pattern Updates Traffic pattern changes will be coming in the next two weeks and will affect the lower level outer roadway.  Long term closure of the lower level outer roadway is to be expected late October.  Detour signage will be posted for traffic flow, pedestrian movement and ground transportation vendors.

Bid opportunities currently available for the project can be reviewed at the Monroe County Purchasing website.

Be sure to follow the progress at RocRenovation.com and on social media! We’re on Facebook (facebook.com/ROCAirport) and Twitter (@ROCAirport).

 

Photo: Site of Prep work to begin between the Parking Garage and the Airport Terminal.

 

 

 