Caisson pouring on the North ramp continues. General Construction bids for the entrance canopy have been reviewed and approved. Passenger Security Checkpoint construction activity is on schedule to begin Fall 2017.

Parking Update All parking lots remain open. The new ROC Airport Smart Phone Lot is open and operating. 

Traffic Pattern Updates None. Traffic patterns remain the same.

Terminal/Security/Gate Update The Hudson News Store (lower level) is in the process of having shelves and lighting installed.  Restroom renovations post-security are nearing completion. Electrical connectivity for the air conditioning control system is progressing. There are no construction-related changes in ticketing or security at this time.

Bid opportunities currently available for the project can be reviewed at the Monroe County Purchasing website.

Be sure to follow the progress at RocRenovation.com and on social media! We’re on Facebook (facebook.com/ROCAirport) and Twitter (@ROCAirport).

 

Photo: Shelving being Installed for the relocated Hudson News Store on the Lower Level.

 

 

 

For General Airport News Visit rocairport.com