The caissons on the North ramp will start being drilled next week. General Construction bids for the entrance canopy have been received and are in the review process. Passenger Security Checkpoint construction activity is on schedule to begin Fall 2017.

Parking Update All parking lots remain open. The new ROC Airport Smart Phone Lot is open and operating. 

Traffic Pattern Updates None. Traffic patterns remain the same.

Terminal/Security/Gate Update Beginning next week, the contractor will commence building walls necessary for the passenger waiting area concession to be relocated on the ground level/baggage claim lobby. Tile installation commenced in the new restrooms being constructed post-security. Electrical connectivity for the air conditioning control system is progressing. There are no construction-related changes in ticketing or security at this time.

Bid opportunities currently available for the project can be reviewed at the Monroe County Purchasing website.

Be sure to follow the progress at RocRenovation.com and on social media! We’re on Facebook (facebook.com/ROCAirport) and Twitter (@ROCAirport).

Photo: Concrete removed on North Ramp for caisson installation.

For General Airport News Visit rocairport.com